PROJECTS
Facility/Industrial Construction Project
138kV Transmission Overhead Project
Brownfield Substation Reconfiguration Project
Transmission 345/138kV Transformer Replacements
Lean Manufacturing & Engineering and Six Sigma Application Project
The 138kV Ring Bus Project
12kV recloser replacement and SCADA installations
Substation transformer design and manufacturing review
Major Equipment Replacement
Substation Rebuilt Project
34kV Distribution Line project
PROJECT DESCRIPTION & CLIENT CHALLENGES:
- Storm hardened the line by installing composite pole structures on every fifth pole.
- Existing substation had (seven) 34kV distribution circuits nested in a small space, all with woodpecker-damaged poles that needed composite pole replacements. Reconfigured and rerouted circuits to accommodate new switches and alignment shifts.
- New alignment for relocating (two) 34 kV lines in dense woods; permanent access roads were required.
- Addressed aging infrastructure and existing clearance concerns found during engineering.
- Multiple construction schedules (Transmission, state highway, client outages, project interfaces) and print versions. Created three sets of construction prints for the different contractors/entities.
- Creation of permitting drawings/coordination (municipal, highway, railroad, FAA).
- Create easement exhibits for new assets and assist in acquiring the easement.
- Designed multiple options to pass a highway and railroad (underground, overhead existing, overhead composite).
- Completely rebuilt portion of the 34kV line adding fiber optics.
RESULTS
The LUZCO project team examined the existing infrastructure to identify damages and problem points. They also completed a heavy underground design to go under a highway and a railroad and reroute (2) 34kV distribution lines to make room for a new substation bay for Transmission circuits. Additionally, the team rerouted a portion of the 34kV line for state bridge construction. Finally, engineering designs were completed, and easements were obtained. Currently, the team is coordinating with different construction schedules/contractors to construct the project.